Canada Commercial Realty

8080d3401986e2543efb2208b11863a0

C.403.680.6130 | francislee@canadacommercialrealty.ca

NEWS

Coastal GasLink pipeline nears finish line with 85.5 per cent complete

As of the end of February, nearly 5,500 workers were employed across northern B.C. on the 670-km natural gas pipeline project
cgl-pipe-stringing
Pipe stringing along the Coastal GasLink pipeline route. |Coastal GasLink

As of March 1, work on the Coastal GasLink pipeline in northeast B.C. was 85.5 per cent complete, according to information released by TC Energy.

Pipeline installation was only 51.5 per cent completed, however, in section 7 of the route, in the area southeast of Houston where the company has encountered ongoing blockades and protests by a group of Wet’suwet’en hereditary chiefs and their supporters.

A year ago, 20 armed protestors attacked a Coastal GasLink work camp near Houston, doing millions of dollars in damage and shutting work down temporarily.  On March 22, 2023, five protestors were arrested after reports of violence against pipeline workers.

Construction of the 670-km natural gas pipeline from west of Dawson Creek to Kitimat employed 5,489 workers as of the end of February, including 1,241 based out of Parsnip Lodge north of Prince George.

“Coastal GasLink begins commissioning process on its Wilde Lake Compressor Station,” a statement released by the company said. “Coastal GasLink’s Wilde Lake Compressor Station has welcomed gas into the facility for the first time. As part of the extensive commissioning process, crews have and continue to check every piece of rotating equipment, every weld and every wire to ensure it has been built as designed with the safety of our workforce, the environment and the surrounding communities at the forefront. The purpose of this early introduction is to conduct further tests on site and decommission the temporary generators currently powering the facility.”